Pine Meadow Drive
Federal contribution
$7,829
Federal share17%
of $45.8K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built
Approved 22 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Vaughan
- Construction start
- Sep 1, 2009(actual)
- Construction end
- Oct 31, 2011(actual)