Muzich Place

Vaughan, Ontario

completeHighways and RoadsISF
Federal contribution
$5,671
Federal share22%

of $26.3K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built

Approved 22 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Vaughan
Construction start
Sep 1, 2009(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast Sep 17, 2009