Grandview Beach Rehabilitation and Asphalt Paving
Federal contribution
$325,251
Federal share33%
of $976.8K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Municipality of Shuniah
- Construction start
- Nov 16, 2009(actual)
- Construction end
- Dec 30, 2010(actual)
Against the original forecast
- Construction start7 weeks lateforecast Oct 1, 2009
- Construction end2 months earlyforecast Mar 15, 2011
Also in Shuniah