Wild Goose Park Multi-Use Lighted Trail
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 7, 2021
202220232024
Built
Approved 5 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Municipality Of Shuniah
- Construction start
- Jul 30, 2024(actual)
- Construction end
- Sep 6, 2024(actual)
Against the original forecast
- Construction start10 months lateforecast Sep 27, 2023
- Construction end2 weeks earlyforecast Sep 23, 2024
Also in Shuniah