Library Accessibility
Federal contribution
$119,992
Federal share31%
of $390.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Moonbeam
- Construction start
- Nov 4, 2009(actual)
- Construction end
- Jun 30, 2010(actual)
Against the original forecast
- Construction start3 weeks lateforecast Oct 15, 2009
- Construction end3 months lateforecast Mar 31, 2010
Also in Moonbeam
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30929 in the federal list. How to read these figures.