Back to projects

Library Accessibility

Moonbeam, Ontario

completeCultureISF
Federal contribution
$119,992
Federal share31%

of $390.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of Moonbeam
Construction start
Nov 4, 2009(actual)
Construction end
Jun 30, 2010(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Oct 15, 2009
  • Construction end3 months lateforecast Mar 31, 2010

Also in Moonbeam

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30929 in the federal list. How to read these figures.