Fire Hall Expansion

Moonbeam, Ontario

completeAdministration, Emergency and Public WorksISF
Federal contribution
$145,833
Federal share33%

of $437.5K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of Moonbeam
Construction start
Nov 30, 2009(actual)
Construction end
Nov 30, 2010(actual)

Against the original forecast

  • Construction end3 months lateforecast Aug 31, 2010

Also in Moonbeam

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30958 in the federal list. How to read these figures.