Retrofit of the Ice Rink at the Al Palladini Community Centre

Vaughan, Ontario

completeSportISF
Federal contribution
$91,667
Federal share33%

of $275.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Vaughan
Construction start
Jun 7, 2010(actual)
Construction end
Oct 22, 2010(actual)

Against the original forecast

  • Construction start5 weeks lateforecast May 1, 2010