Martin Grove Road Improvement
Federal contribution
$744,246
Federal share28%
of $2.7M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Vaughan
- Construction start
- Sep 21, 2009(actual)
- Construction end
- Dec 31, 2010(actual)
Against the original forecast
- Construction start6 months earlyforecast Apr 1, 2010
- Construction end10 months earlyforecast Oct 31, 2011