Upgrades to the Michipicoten Memorial Community Centre
Federal contribution
$58,333
Federal share33%
of $175.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Municipality of Wawa
- Construction start
- Aug 19, 2009(actual)
- Construction end
- Jun 23, 2010(actual)
Also in Wawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30977 in the federal list. How to read these figures.