Back to projects

Upgrades to the Michipicoten Memorial Community Centre

Wawa, Ontario

completeSportISF
Federal contribution
$58,333
Federal share33%

of $175.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Municipality of Wawa
Construction start
Aug 19, 2009(actual)
Construction end
Jun 23, 2010(actual)