Frenchmans Rock Road Upgrade
Federal contribution
$53,909
Federal share33%
of $163.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Lake of the Woods
- Construction start
- Sep 14, 2009(actual)
- Construction end
- Sep 30, 2010(actual)
Against the original forecast
- Construction start2 weeks lateforecast Aug 31, 2009