Water Treatment Plant Upgrades

Lake of the Woods, Ontario

completeDrinking WaterSCF
Federal contribution
$940,000
Federal share33%

of $2.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 11, 2015
201620172018201920202021
Built

Approved 4 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Big Grassy First Nation
Construction start
May 19, 2020(actual)
Construction end
May 31, 2021(actual)

Against the original forecast

  • Construction start14 months lateforecast Mar 15, 2019
  • Construction end16 months earlyforecast Oct 15, 2022

Also in Lake of the Woods

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46233 in the federal list. How to read these figures.