Consolidated Maintenance Facility Improvements

Kitchener, Ontario

completeHighways and RoadsISF
Federal contribution
$4.7M
$4,666,667
Federal share33%

of $14.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Kitchener
Construction start
Oct 1, 2009(actual)
Construction end
May 2, 2011(actual)

Against the original forecast

  • Construction start7 months earlyforecast May 1, 2010
  • Construction end6 months earlyforecast Oct 31, 2011