Jessie Street and George Street Sewer Separation
Federal contribution
$451,850
Federal share30%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Brockville
- Construction start
- Jun 1, 2010(actual)
- Construction end
- Nov 18, 2010(actual)
Against the original forecast
- Construction end6 weeks earlyforecast Dec 31, 2010
Also in Brockville
- Brockville Water Pollution Control Centre Upgrade$22.3M
- Construction of the Maritime Discovery Centre of the 1000 Islands (MDC)$5.7M
- HVAC, Bottle Water Filling Station, Portable, Retrofits, Wifi, Windows$5.2M
- Automatic Door Opener; Video Camera Childcare Project Group; Washroom Project Group; Site Project Group; HVAC Ventilation Upgrades$2.1M
- To replace aging HVAC Equipment and Controls.$2.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31073 in the federal list. How to read these figures.