Atwood Road #2 Upgrade

Dawson, Ontario

completeHighways and RoadsISF
Federal contribution
$29,333
Federal share33%

of $88.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of Dawson
Construction start
Aug 5, 2009(actual)
Construction end
May 28, 2010(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jul 6, 2009
  • Construction end4 months earlyforecast Sep 30, 2010