Upgrade Dawson Public Works Building
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 7, 2021
2022
Built
Approved 2 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Township of Dawson
- Construction start
- Aug 8, 2022(actual)
- Construction end
- Nov 28, 2022(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jul 15, 2022
- Construction end4 weeks earlyforecast Dec 23, 2022