Back to projects

County Road 44 Improvements

Ramara, Ontario

completeHighways and RoadsISF
Federal contribution
$1.7M
$1,666,666
Federal share33%

of $5.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
County of Simcoe
Construction start
Jul 1, 2010(actual)
Construction end
Sep 30, 2010(actual)

Against the original forecast

  • Construction end6 months earlyforecast Mar 31, 2011

Also in Ramara

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31116 in the federal list. How to read these figures.