Reconstruction of Lovely Day Park Playground
Federal contribution
$60,950
Federal share40%
of $152.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 8, 2021
2022
Built
Approved 3 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Township of Ramara
- Construction start
- May 23, 2021(actual)
- Construction end
- Jun 18, 2022(actual)
Against the original forecast
- Construction start12 months earlyforecast Jun 1, 2022
- Construction end2 months earlyforecast Aug 31, 2022
Also in Ramara
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57651 in the federal list. How to read these figures.