County Road 14 Resurfacing

Huron East, Ontario

completeHighways and RoadsISF
Federal contribution
$197,251
Federal share11%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
County of Huron
Construction start
Aug 1, 2009(actual)
Construction end
Apr 14, 2010(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Sep 1, 2009
  • Construction end2 weeks lateforecast Mar 31, 2010