Municipal Road 80 (Paris Street), Kathleen Street to York Street

Greater Sudbury, Ontario

completeHighways and RoadsISF
Federal contribution
$3.8M
$3,833,333
Federal share33%

of $11.5M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Greater Sudbury
Construction start
Aug 1, 2009(actual)
Construction end
Jul 31, 2011(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jun 15, 2009
  • Construction end2 months earlyforecast Sep 30, 2011

Also in Greater Sudbury

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31179 in the federal list. How to read these figures.