Churchill Road Rehabilitation
Drummond/North Elmsley, Ontario
Federal contribution
$359,647
Federal share30%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Drummond-North Elmsley
- Construction start
- Aug 10, 2009(actual)
- Construction end
- Jun 7, 2010(actual)
Against the original forecast
- Construction start6 weeks lateforecast Jul 1, 2009
- Construction end6 months lateforecast Nov 30, 2009