Back to projects

Churchill Road Rehabilitation

Drummond/North Elmsley, Ontario

completeHighways and RoadsISF
Federal contribution
$359,647
Federal share30%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Aug 10, 2009(actual)
Construction end
Jun 7, 2010(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jul 1, 2009
  • Construction end6 months lateforecast Nov 30, 2009

Also in Drummond/North Elmsley