Back to projects

Landfill Office Trailer Replacement

Drummond/North Elmsley, Ontario

completeSolid Waste ManagementCVRIS
Federal contribution
$80,000
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 15, 2021
2022
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Nov 10, 2021(actual)
Construction end
Feb 6, 2022(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Sep 15, 2021
  • Construction end10 months earlyforecast Dec 6, 2022

Also in Drummond/North Elmsley