Blam Beach Road Improvements
Federal contribution
$103,033
Federal share30%
of $340.9K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Tiny
- Construction start
- Apr 15, 2010(actual)
- Construction end
- Nov 25, 2010(actual)
Against the original forecast
- Construction end4 months earlyforecast Mar 31, 2011
Also in Tiny
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31231 in the federal list. How to read these figures.