Schedule

Announced and approvedJun 16, 2017
Built

Approved 4 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of Tiny
Construction start
Sep 10, 2017(actual)
Construction end
Sep 29, 2017(actual)

Against the original forecast

  • Construction start6 months lateforecast Mar 1, 2017
  • Construction end2 months earlyforecast Nov 30, 2017