County Road 25 from County Road 42 to Highway 401 Pavement Rehabilitation
Federal contribution
$254,971
Federal share33%
of $764.9K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built
Approved 22 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- County of Essex
- Construction start
- Jun 8, 2010(actual)
- Construction end
- Aug 20, 2010(actual)
Against the original forecast
- Construction start9 months lateforecast Aug 31, 2009
- Construction end3 months earlyforecast Nov 30, 2010
Also in Lakeshore
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31234 in the federal list. How to read these figures.