Ridge Road Infrastructure Improvements
Federal contribution
$2.0M
$1,961,333
Federal share33%
of $5.9M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Fort Erie
- Construction start
- Apr 5, 2010(actual)
- Construction end
- Sep 30, 2011(actual)
Against the original forecast
- Construction start5 weeks lateforecast Mar 1, 2010
- Construction end4 weeks earlyforecast Oct 31, 2011
Also in Fort Erie
- Fort Erie Peace Bridge Approaches$21.0M
- Frenchmans Creek Sewage Servicing$5.3M
- Construction of the North Crescent Park Storm Drainage System$1.1M
- Murray Street Sanitary Sewer - Replacement of vitrified clay pipe$421.4K
- Fort Erie - Alternative Secondary School Program - COVID Infrastructure Retrofits$280.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31270 in the federal list. How to read these figures.