Back to projects

Frenchman’s Creek Sewage Servicing

Fort Erie, Ontario

completeWastewaterISF
Federal contribution
$5.3M
$5,280,848
Federal share26%

of $20.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Oct 19, 2009(actual)
Construction end
Jun 30, 2011(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Sep 1, 2009
  • Construction end4 months earlyforecast Oct 31, 2011

Also in Fort Erie

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32303 in the federal list. How to read these figures.