Realignment of the Intersection of Rue de lÉglise and Rue des Pins
Federal contribution
$78,969
Federal share31%
of $255.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Dubreuilville
- Construction start
- Aug 1, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start4 months lateforecast Apr 1, 2010
Also in Dubreuilville
- Identification and Development of a New Municipal Landfill Site$225.1K
- Water treatment plant repairs - Inspect and repair or replace valves and piping in pump house$21.0K
- Water distribution maintenance - Swabbing of distribution system$11.9K
- Water distribution repairs - Replace seals and valves for 2 hydrants$9.7K
- Water treatment plant upgrade - Perform engineering study to design and install a contact time return line from contact chamber to analyzer.$7.5K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31352 in the federal list. How to read these figures.