Identification and Development of a New Municipal Landfill Site
Federal contribution
$225,133
Federal share33%
of $675.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 18, 2016
20162018202020222024
Built
Approved 4 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Township of Dubreuilville
- Construction start
- Jun 15, 2018(actual)
- Construction end
- Dec 14, 2023(actual)
Against the original forecast
- Construction end3 months lateforecast Aug 31, 2023
Also in Dubreuilville
- Realignment of the Intersection of Rue de lÉglise and Rue des Pins$79.0K
- Water treatment plant repairs - Inspect and repair or replace valves and piping in pump house$21.0K
- Water distribution maintenance - Swabbing of distribution system$11.9K
- Water distribution repairs - Replace seals and valves for 2 hydrants$9.7K
- Water treatment plant upgrade - Perform engineering study to design and install a contact time return line from contact chamber to analyzer.$7.5K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46391 in the federal list. How to read these figures.