Rehabilitation of Municipal Wells
Federal contribution
$13,162
Federal share22%
of $60.6K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Black River-Matheson
- Construction start
- Nov 15, 2009(actual)
- Construction end
- Mar 31, 2011(actual)