Upgrade Programmable Logic Controller (PLC)
Federal contribution
$50,000
Federal share45%
of $110.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
2018
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Black River-Matheson
- Construction start
- Jul 4, 2017(actual)
- Construction end
- Nov 14, 2018(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Aug 1, 2017
- Construction end6 weeks lateforecast Sep 30, 2018