Upgrade Programmable Logic Controller (PLC)

Black River-Matheson, Ontario

completeDrinking WaterCWWF
Federal contribution
$50,000
Federal share45%

of $110.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
2018
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jul 4, 2017(actual)
Construction end
Nov 14, 2018(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Aug 1, 2017
  • Construction end6 weeks lateforecast Sep 30, 2018