The Woodbridge Memorial Tower and Park Site Rehabilitation - Landscaping
Federal contribution
$56,281
Federal share33%
of $170.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Vaughan
- Construction start
- Oct 15, 2009(actual)
- Construction end
- Nov 8, 2010(actual)
Against the original forecast
- Construction start2 weeks earlyforecast Oct 31, 2009
- Construction end6 weeks lateforecast Sep 30, 2010
Also in Vaughan