Wyndham Street: Carden to Wellington - Guelph

Guelph, Ontario

completeHighways and RoadsISF
Federal contribution
$2.8M
$2,800,000
Federal share33%

of $8.4M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
201020112012
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Guelph
Construction start
Sep 14, 2009(actual)
Construction end
May 11, 2012(actual)

Against the original forecast

  • Construction end3 weeks earlyforecast May 31, 2012