County Road 23 from Highway 3 to County Road 27 and County Road 27 from Highway 3 to County Road 23 Pavement Preservation

Essex, Ontario

completeHighways and RoadsISF
Federal contribution
$321,282
Federal share33%

of $963.8K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built

Approved 22 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
County of Essex
Construction start
Aug 21, 2009(actual)
Construction end
Nov 30, 2009(actual)

Also in Essex