Back to projects

Parks Rehabilitation

St. Joseph, Ontario

completeRecreationISF
Federal contribution
$50,000
Federal share33%

of $150.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of St. Joseph
Construction start
Aug 10, 2009(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Jun 15, 2009

Also in St. Joseph

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31420 in the federal list. How to read these figures.