Rehabilitation of Richards Landing Marina
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2021
2022
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Township of St. Joseph
- Construction start
- Sep 22, 2022(actual)
- Construction end
- Nov 2, 2022(actual)
Against the original forecast
- Construction start2 weeks lateforecast Sep 6, 2022
- Construction end8 weeks earlyforecast Dec 31, 2022
Also in St. Joseph
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59420 in the federal list. How to read these figures.