St. Francis de Sales Rehabilitation and Retrofit
Federal contribution
$852,473
Federal share33%
of $2.6M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Ajax
- Construction start
- Jun 16, 2010(actual)
- Construction end
- Jul 6, 2011(actual)
Against the original forecast
- Construction start2 weeks earlyforecast Jun 30, 2010
- Construction end5 weeks lateforecast May 31, 2011