Grandview Redevelopment
Federal contribution
$17.5M
$17,500,000
Federal share22%
of $78.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 8, 2019
202020212022202320242025
Built
Approved 6 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Grandview Children's Centre
- Construction start
- Oct 1, 2022(actual)
- Construction end
- Oct 18, 2024(actual)
Against the original forecast
- Construction end8 weeks lateforecast Aug 23, 2024
Also in Ajax
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54361 in the federal list. How to read these figures.