Back to projects

Beatrice Way

Vaughan, Ontario

completeHighways and RoadsISF
Federal contribution
$41,338
Federal share19%

of $218.8K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built

Approved 22 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Vaughan
Construction start
Sep 2, 2009(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start7 months earlyforecast Apr 1, 2010

Also in Vaughan

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31526 in the federal list. How to read these figures.