Back to projects

Chilmar Crescent

Vaughan, Ontario

completeHighways and RoadsISF
Federal contribution
$18,035
Federal share19%

of $97.1K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Vaughan
Construction start
Sep 25, 2009(actual)
Construction end
Jun 30, 2010(actual)

Against the original forecast

  • Construction start6 months earlyforecast Apr 1, 2010
  • Construction end5 months earlyforecast Nov 30, 2010

Also in Vaughan

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31569 in the federal list. How to read these figures.