Longview Crescent
Federal contribution
$7,767
Federal share33%
of $23.3K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Vaughan
- Construction start
- Sep 2, 2009(actual)
- Construction end
- Jun 30, 2010(actual)
Against the original forecast
- Construction end5 months earlyforecast Nov 30, 2010
Also in Vaughan
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31612 in the federal list. How to read these figures.