Sewer and Watermain Rehabilitation
Federal contribution
$833,334
Federal share33%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built
Approved 22 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Kitchener
- Construction start
- Oct 5, 2009(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start5 months earlyforecast Mar 1, 2010
Also in Kitchener
- Stormwater Network Adaptation$50.0M
- Aquatic Centre RBJ Schlegel Park$9.8M
- Installing mechanical ventilation in buildings where none currently exist; Window repair or replacement for fresh air intake$7.9M
- HVAC Upgrades; Upgrading wireless access points; Window replacement; Washroom upgrades; Installing cooling / air conditioning units; room partition replacement$7.6M
- Kitchener Public Library Southwest Community Library$6.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31661 in the federal list. How to read these figures.