New Municipal Building for Algoma Public Health

Sault Ste. Marie, Ontario

completeOtherISF
Federal contribution
$7.3M
$7,333,333
Federal share33%

of $22.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Sault Ste. Marie
Construction start
Oct 14, 2009(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Sep 27, 2009

Also in Sault Ste. Marie

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31675 in the federal list. How to read these figures.