Mukwa Waakaaigan
Federal contribution
$7.1M
$7,102,860
Federal share16%
of $43.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 20, 2021
today
202220232024202520262027
BuiltForecast
Approved 3 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Algoma University
- Construction start
- Jun 1, 2025(actual)
- Construction end
- Feb 18, 2027(forecast)
Against the original forecast
- Construction start4 weeks lateforecast May 1, 2025
Also in Sault Ste. Marie
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57562 in the federal list. How to read these figures.