Upgrades to Chinguacousy Park

Brampton, Ontario

completeRecreationISF
Federal contribution
$8.1M
$8,090,080
Federal share33%

of $24.5M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Brampton
Construction start
Jan 4, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Nov 16, 2009
  • Construction end4 weeks lateforecast Sep 30, 2011

Also in Brampton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31691 in the federal list. How to read these figures.