Protecting our future: Flood mitigation and physical, economic, social and cultural resilience for historic downtown Brampton, on by reconstructing 600M of the concrete Etobicoke Creek bypass channel

Brampton, Ontario

underwayDisaster MitigationDMAF
Federal contribution
$38.9M
$38,852,397
Federal share40%

of $97.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 18, 2020
today
2021202320252027
BuiltForecast

Approved 5 weeks before the announcement.

Program
Disaster Mitigation and Adaptation Fund
Construction start
Nov 24, 2025(actual)
Construction end
Mar 31, 2028(forecast)

Also in Brampton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52903 in the federal list. How to read these figures.