Zero Carbon Retrofit of Susan Fennell Sportsplex

Brampton, Ontario

underwayRecreationGICB
Federal contribution
$15.7M
$15,743,000
Federal share40%

of $39.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 19, 2022
202320242025
BuiltForecast

Approved 8 weeks before the announcement.

Program
Green and Inclusive Community Buildings Program
Construction start
Apr 15, 2024(actual)
Construction end
Sep 15, 2025(forecast)

Against the original forecast

  • Construction start23 months lateforecast May 9, 2022

Also in Brampton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64701 in the federal list. How to read these figures.