Lucknow and District Firehall
Ashfield-Colborne-Wawanosh, Ontario
Federal contribution
$375,000
Federal share33%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Ashfield-Colborne-Wawanosh
- Construction start
- Oct 1, 2009(actual)
- Construction end
- Jun 29, 2010(actual)
Against the original forecast
- Construction end3 months earlyforecast Sep 30, 2010
Also in Ashfield-Colborne-Wawanosh
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31693 in the federal list. How to read these figures.