Investigate and implement a rehabilitation or treatment strategy for arsenic in the Dungannon Wells
Ashfield-Colborne-Wawanosh, Ontario
Federal contribution
$50,000
Federal share6%
of $842.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
20172018
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Ashfield-Colborne-Wawanosh
- Construction start
- Apr 1, 2016(actual)
- Construction end
- Mar 31, 2018(actual)
Against the original forecast
- Construction start10 months earlyforecast Feb 1, 2017
- Construction end12 months earlyforecast Mar 31, 2019
Also in Ashfield-Colborne-Wawanosh
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48351 in the federal list. How to read these figures.