Faraday Landfill Capacity Reclamation

Faraday, Ontario

completeSolid Waste ManagementISF
Federal contribution
$123,837
Federal share33%

of $371.5K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of Faraday
Construction start
Aug 10, 2009(actual)
Construction end
Nov 18, 2009(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Jun 15, 2009
  • Construction end4 months earlyforecast Mar 31, 2010

Also in Faraday

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31771 in the federal list. How to read these figures.