Replacement of the Old Hastings Road Bridge

Faraday, Ontario

completeHighways and RoadsRNIS
Federal contribution
$490,070
Federal share60%

of $816.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 19, 2020
20212022
Built

Approved 3 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Faraday
Construction start
Aug 3, 2021(actual)
Construction end
Jul 29, 2022(actual)

Against the original forecast

  • Construction end4 months lateforecast Mar 31, 2022