Replacement of the Old Hastings Road Bridge
Federal contribution
$490,070
Federal share60%
of $816.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 19, 2020
20212022
Built
Approved 3 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Faraday
- Construction start
- Aug 3, 2021(actual)
- Construction end
- Jul 29, 2022(actual)
Against the original forecast
- Construction end4 months lateforecast Mar 31, 2022